THE MEADOWS LIQUID ROAD SURFACING

sealcoat schedule THE MEADOWS LIQUID ROAD SURFACING

The Meadows community street surfacing with Liquid Road Ultrablend surfacer will begin on or after MONDAY, JULY 25, 2022 through THURSDAY JULY 28,2022. Weather and pavement conditions permitting.

Jefferson County Highway Department letter to residents.

The Meadows Liquid Road Surfacing Area.

See below for the daily surfacing schedule.

Streets will NOT be closed off completely. Streets will be surfaced only one side of the street each day. When surfacing is applied on one half of the street, the opposite side will be ONE WAY in the normal direction. Cul-de-sac streets will be TWO WAY in the lane not being surfaced. Streets will be coned off and Flaggers will direct traffic where required.

Signs will be posted. We will provide traffic control. Please obey the flaggers if present. DO NOT park on the streets. Directional signs and NO PARKING signs will be posted. We will provide traffic control. Please obey the flaggers.

DO NOT park on the streets. Traffic must be able to use the side of the street we are not surfacing. Tow trucks will be on standby to remove vehicles parked in the street. Please contact any contractors or lawn service providers and notify them of these restrictions.

Surfacing is weather-dependent. Rain will alter the schedule. If your street is rained out, it will be scheduled for the next day. The entire schedule will be pushed back according to the weather.

LIQUID ROAD Ultrablend is an applied liquid (Application Video). It is a two-coat system. We will apply the first coat in the morning starting at 7 AM. We will apply the second coat as quickly as drying time allows. We expect to have the second coat applied by early afternoon. If we have sun, breeze, and low humidity, we should have the street opened by 7 PM.

DO NOT drive through wet surfacing. This is what happens. Driving through or walking on wet Sealer will track and splash on cars. When Liquid Road is dry, it will not track. If orange cones are in place, the surface is still wet – DO NOT drive or walk in the coned-off area.

DAILY SURFACING SCHEDULE

MONDAY  7-25-22  –  RED AREA

TUESDAY 7-26-22 –  RAINED OUT

WEDNESDAY  7-27-22  –  RAINED OUT

THURSDAY  7-28-22  –  BLUE AREA

FRIDAY  7-29-22  –  WHITE AREA

MONDAY 8-1-22  RAINED OUT

TUESDAY  8-2-22  –  GREEN AREA

Please check this website for updates.