South Bend Liquid Road

sealcoat schedule South Bend Liquid Road

South Bend Liquid Road Project 2023

As part of the City’s Pavement Preservation Program the streets in your neighborhood will receive a Liquid Road surfacing treatment.

South Bend Liquid Road Street Locations

South Bend Letter to Residents

See below for the daily surfacing schedule. Click on the street name for the daily work area.

Streets will be closed off completely for cracksealing and surfacing. Streets will be closed completely for two days . Streets will be barricaded and coned off.

Directional signs and NO PARKING signs will be posted.
We will provide traffic control. Please obey flaggers if present.

DO NOT park on the streets. Tow trucks will be on standby to remove
vehicles parked on the street. Please contact any contractors, lawn
service providers and deliveries to notify them of these restrictions.

Surfacing is weather-dependent. Rain will alter the schedule. If your
street is rained out, it will be scheduled for the next day. The entire
schedule will be pushed back according to the weather.

LIQUID ROAD Ultrablend is an applied liquid (Application Video). It is a two-coat system. We will apply the first coat in the morning starting at 7 AM.
We will apply the second coat as quickly as drying time allows. We
expect to have the second coat applied by early afternoon. The street will remain closedthat night to allow proper drying time for the material. The street is expected to be opened at approx 9AM the next morning. Please plan accordingly.

DO NOT drive through wet surfacing. This is what happens. Driving through or walking on wet Sealer will track and splash on cars. When Liquid Road is dry, it will not track. If barricades and orange cones are in place, the surface is still wet – DO NOT drive or walk in the coned-off area.

DAILY SURFACING SCHEDULE

MONDAY       8-28-23    RED      Cleaning and Cracksealing

Iowa             Western to Jefferson     

TUESDAY     8-2923     RED       Liquid Road Application

Iowa            Western to Jefferson

WEDNESDAY    8-30-23     BLUE   Cleaning and Cracksealing

Kenmore      Western to Jefferson

Kenmore       Washington to Linden

THURSDAY         8-31-23       BLUE     Liquid Road Application

Kenmore       Western to Jefferson

Kenmore     Washington to Linden

TUESDAY      9-5-23      GREEN    Cleaning and Cracksealing

Illinois     Western to Jefferson

Illinois      Jefferson to Washington

Illinois      Washington to Linden

WEDNESDAY  9-6-23   GREEN      Liquid Road Application

RAINED OUT

Illinois     Western to Jefferson

Illinois      Jefferson to Washington

Illinois      Washington to Linden

Thursday 9-7-23       GREEN         Liquid Road Application

RAINED OUT

Illinois        Western to Jefferson

FRIDAY   9-8-23       GREEN      Liquid Road Application

Illinois        Western to Jefferson

 

PLEASE FOLLOW THIS WEBSITE FOR SCHEDULE UPDATES